- BH?s funding for the road works was given to the Council, so it?s separate from anything to do with building the flats.
- he thinks work is about a month behind schedule and he?s now hoping it will be completed by Friday 3 October 2008. Delays have been caused because of bad weather and the old water mains: they?re now working by hand to avoid damaging the water mains again.
- they?re working on the new carriageway this week and will hopefully start the new footways next week. After the kerbs have been done they?ll be able to finish the carriageway and lay the paving slabs.
- there may be a bit of a problem with the footway on the northern side of Hindsley?s Place: the building site hoarding is set on the kerbline so Mick will see if it can be moved back so he can work on the footway.