Then I spotted that the item was dated July 2011 with proposals that work be carried out between September and October 2011 - at that point a delay of some four years.
Four things emerge; it looks as if specifications had been agreed for the cladding; agreed for the lighting; installation of CCTV seemed integral to the proposal and Network Rail (NR) had committed to obtaining a Temporary Closure for the subway for the duration of the works.
Less clear was what specification was to be applied to the subway floor surfaces and steps - and if my memory is correct we have an existing CCTV system installed - so is the CCTV system being upgraded and to where will it be connected. Are there any outstanding track-bed drainage issues to be resolved ?
Can anyone provide a link to where an up-to-date proposal and specification is located ?
Has a current project timeline been approved and is NR's Temporary Closure application still current? Is the necessary funding still in place and under what organisation's auspices is the work to be carried out - NR or LBL?